Shipping and Lead Time

Production 7-30 days, air 7-12 days, rail 20-30 days, sea 25-35 days, local certification about one month, Chinese New Year cut-off and Incoterms.

Lead time is production plus transit plus any local certification. We quote the stages separately so the project can plan around the real path, not a single optimistic number.

Planning ranges

StageTypical range
Production7–30 days, depending on product and customization
Air freight7–12 days
Rail20–30 days
Sea freight25–35 days
Local certificationAbout 1 month, when required
Chinese New Year cut-offAbout 15 days before the holiday

Incoterms

We normally quote FOB, CIF or DDP. The Incoterm is stated in the quotation; it decides who arranges freight, insurance, import clearance and the final delivery.

What can move the date

  • Custom CCT, housing, logo or packaging.
  • Certificate or test report that has to be issued before shipment.
  • Destination inspection, import licence or local certification.
  • Peak season, port congestion or a public holiday.

What we do not promise

We do not promise “1–2 week delivery” for a full order. The production range and the transit range are separate, and local certification can add a month. The quotation states the lead time for the exact order.

Send the destination and deadline through the contact page and we will quote the realistic path.