Shipping and Lead Time
Production 7-30 days, air 7-12 days, rail 20-30 days, sea 25-35 days, local certification about one month, Chinese New Year cut-off and Incoterms.
Lead time is production plus transit plus any local certification. We quote the stages separately so the project can plan around the real path, not a single optimistic number.
Planning ranges
| Stage | Typical range |
|---|---|
| Production | 7–30 days, depending on product and customization |
| Air freight | 7–12 days |
| Rail | 20–30 days |
| Sea freight | 25–35 days |
| Local certification | About 1 month, when required |
| Chinese New Year cut-off | About 15 days before the holiday |
Incoterms
We normally quote FOB, CIF or DDP. The Incoterm is stated in the quotation; it decides who arranges freight, insurance, import clearance and the final delivery.
What can move the date
- Custom CCT, housing, logo or packaging.
- Certificate or test report that has to be issued before shipment.
- Destination inspection, import licence or local certification.
- Peak season, port congestion or a public holiday.
What we do not promise
We do not promise “1–2 week delivery” for a full order. The production range and the transit range are separate, and local certification can add a month. The quotation states the lead time for the exact order.
Send the destination and deadline through the contact page and we will quote the realistic path.